John Hodgins Engineering Building

Primary Issues

  • Old single pane windows
  • Old, inefficient fluorescent lighting fixtures
  • 7 ventilation systems in 59 and 72 additions with deteriorating coils, drip trays and numerous deficiencies noted from 2000 report
  • Five pumps require replacement
  • Interior fancoil heating/cooling units are over 30 years old, manually controlled, and failing
  • Old motor control centres with obsolete components

Renewal Measures

Lighting Retrofit - install new fluorescent fixtures or retrofit old fixtures as required. Install new
suspended ceiling in some areas. Occupancy sensors switches for offices.

  • Improve space comfort & quality
  • Positive environmental & health impact
  • Improve efficiency (energy reduction)
  • Reduces maintenance requirement
  • Meet current building standards

New Windows - replace windows with double glazing, operable units.

  • Improve space comfort & quality
  • Improve efficiency (energy reduction)
  • Reduces maintenance requirement
  • Meet current building standards

New Pumps - replace 5 pumps with new c/w variable speed operation

  • Improve efficiency (energy reduction)
  • Reduces maintenance requirement

New MCC - replace 2 motor control centres with new.

  • Reduces maintenance requirement
  • Meet current building standards

New AHUs - Replace AHU 1 to 6 with new units. Refurbish system SF7. Rebalance system and new digital controls.

  • Improve space comfort & quality
  • Positive environmental & health impact
  • Meet current building standards

Weather-stripping - install new weather-stripping to exterior doors.

  • Improve space comfort & quality
  • Improve efficiency (energy reduction)

New Toilets - install new low flush toilets with auto-flush valves.

  • Improve efficiency (energy reduction)
  • Meet current building standards

 


Related Topics

Campus Renewal Partnership Building Profiles
View project information and profiles for all the buildings involved in the CRP
Building Profile Printable PDF Version 158kb

John Hodgins Engineering Building

John Hodgins Engineering
Building Facts

  • Constructed in 1959,72,89. Annex renovated in 1991
  • 240,677 sq/ft (22,360 sq/m)


 
 