Campus Construction and Renovation Projects

Bates Residence–Replacement of Kitchen Plumbing Risers–Phase 2

Job No: 2933
Project No:

Construction Mgr./Contractor: Tarbutt Construction
Consultant:: Atkinson Engineering Inc.
Project Description: Replacement of 10 plumbing risers including the replacement of the kitchen cabinets.The project is estimated to begin on 5/3/2010 and end on 8/13/2010. For more information please contact Project Manager Joe Medeiros at extension 27789.

 

Boiler Replacement, Clarke Centre

Job No:
Project No:
914
Construction Mgr./Contractor:
Consultant:: Atkinson Engineering Inc
Project Description: Design has begun for replacement of three of the five boilers. Modifications to the roof will be required to allow for extraction of Boiler #1 and craning in a new 100,000 lb. unit. Once this unit is on line, the other two boilers will be decommissioned, removed and replaced with one 50,000 lb. unit. Both of the new boilers will include a super heat section and economizers for efficiency. They will be capable of running on natural gas or oil. It is expected that Boiler #1 will be installed within a year.The project is estimated to begin on 4/30/2010 and end on 4/30/2011. For more information please contact Project Manager Stuart Young at extension 26125.

 

Brandon Hall - Air Handling Unit Replacement

Job No: 2971-2
Project No:

Construction Mgr./Contractor: TBA
Consultant:: Atkinson Engineering Inc.
Project Description: Replacing old air handler with new one and updating the controls.The project is estimated to begin on 6/14/2010 and end on 8/13/2010. For more information please contact Project Manager Joe Medeiros at extension 27789.

 

Brandon Hall – Window Replacement

Job No: 2971-1
Project No:

Construction Mgr./Contractor: Alwind Industries
Consultant:: Halsall Associates Limited
Project Description: Replacing all the windows in Brandon Hall with energy efficient ones.The project is estimated to begin on 5/10/2010 and end on 8/13/2010. For more information please contact Project Manager Joe Medeiros at extension 27789.

 

Edwards Hall – Installation of Instantaneous Hot Water Heater

Job No: 2971-5
Project No:

Construction Mgr./Contractor: TBA
Consultant:: Atkinson Engineering Inc.
Project Description: Replacing of the old hot water tank with energy efficient instantaneous hot water heaters.The project is estimated to begin on 6/14/2010 and end on 8/13/2010. For more information please contact Project Manager Joe Medeiros at extension 27789.

 

Emergency Power Generators, E.T. Clarke Centre

Job No:
Project No:
907
Construction Mgr./Contractor: Comstock
Consultant:: P.B. Engineering
Project Description: Two new emergency generators are being installed on the roof of the E.T. Clarke Centre. Each generator is capable of generating 1,250 KW’s of power. This will double our emergency power generating capability and will serve our needs for the foreseeable future. The project includes running new main feeder cables to the north, to feed the new Stadium and sports complexes, as well as routing to the south, to feed the new Engineering Technology Building. The new additions will be on line by the end of April.The project is estimated to begin on 8/1/2008 and end on 9/30/2009. For more information please contact Project Manager Stuart Young at extension 26125.

 

Exterior Restoration of Hamilton Hall Masonry

Job No:
Project No:
943
Construction Mgr./Contractor: Empire Restoration Ltd.
Consultant::
Project Description: Structural repairs to south east gable, remove damaged mortor joints and repoint, repair two water drainage deficiencies, and replace broken / missing building stone.The project is estimated to begin on 5/25/2010 and end on 8/1/2010. For more information please contact Project Manager Bernie Shaw at extension 27747.

 

Moulton Hall – Replacement of Corridor and Common Room Carpet

Job No: 2971-6
Project No:

Construction Mgr./Contractor: TBA
Consultant::
Project Description: Replace carpet in corridor and common rooms.The project is estimated to begin on 7/1/2010 and end on 8/13/2010. For more information please contact Project Manager Joe Medeiros at extension 27789.

 

NRB West Addition

Job No:
Project No:
939
Construction Mgr./Contractor: Ira McDonald Construction Ltd.
Consultant::
Project Description: The NRB West Addition is a 3 storey addition to the Nuclear Research Building. The first and second floors will house research laboratories for several different groups of researchers and their staff. The third floor will be offices for the same research groupsThe project is estimated to begin on 10/8/2010 and end on 3/31/2011. For more information please contact Project Manager David Heatlie and Stuart Gilmour at extension 23051/23062.

 

Security Improvements

Job No:
Project No:
909
Construction Mgr./Contractor: STF Construction
Consultant:: VRM
Project Description: An emergency notification system comprising of 3 sirens will be installed on campus. The system will be used to alert students, staff and faculty of emergency situations. Two of the sirens will be installed on 50’ high poles, one on the boulevard by Mary Keyes Residence, in line with the stack and the other will be next to the ravine by the Alumni Memorial Building. The final siren was installed on the JHE penthouse roof on August 6. Commissioning of this siren will be completed before the end of the month.The project is estimated to begin on 3/1/2008 and end on 6/30/2009. For more information please contact Project Manager Bernie Shaw at extension 27747.

 

Strobic Fan Replacement, ABB

Job No:
Project No:
913
Construction Mgr./Contractor:
Consultant:: Atkinson Engineering Inc
Project Description: A high plume fan system will be installed on the Physics Wing of the Arthur Bourns Building. This system will take lab and fume hood exhaust and dilute it, while expelling it high into the atmosphere. The fume hoods will get new controls and monitors. This installation will be similar to the exhaust system that was installed on the research wing of the same building last year. The roof on this wing of the building is over 40 years old and will be replaced as part of this project. Also the Motor Control Centre (MCC) for this wing will be replaced.The project is estimated to begin on 6/30/2009 and end on 9/30/2009. For more information please contact Project Manager Joe Medeiros at extension 27789.

 

The Centre for Spinal Injury Cancer Research and Rehabillitation

Job No:
Project No:
938
Construction Mgr./Contractor: STF Construction Ltd.
Consultant::
Project Description: 20,000 square feet, 3 stored addition to IWC consisting of labs, rehabilitation facilities, offices and a 72 seat lecture theatre.The project is estimated to begin on 5/26/2010 and end on 3/31/2010. For more information please contact Project Manager Bernie Shaw at extension 27747.

 

University Hall Mechanical Upgrades

Job No:
Project No:
946
Construction Mgr./Contractor: TESC - Shewfelt
Consultant::
Project Description: This project involves the removal of all the hot water heating and chilled water, piping and insulation, and the installation of new piping and insulation in the basement of University hall.The project is estimated to begin on 5/3/2010 and end on 7/30/2010. For more information please contact Project Manager David Heatlie at extension 23051.

 

Whidden Hall – Heating System Replacement – Phase 1

Job No: 2971-3
Project No:

Construction Mgr./Contractor:
Consultant::
Project Description: Replacement of the heating system in one wing of Whidden Hall. Replacement of the wall fin system with fan coil units.The project is estimated to begin on 6/7/2010 and end on 8/13/2010. For more information please contact Project Manager Joe Medeiros at extension 27789.

 

Window Replacement, CNH

Job No:
Project No:
944
Construction Mgr./Contractor: Unique Restoration
Consultant:: I.R.C
Project Description: Replace the windows on the East face of CNHThe project is estimated to begin on and end on 8/20/2010. For more information please contact Project Manager Stuart Young at extension 26125.

 

Woodstock Hall – Fan Coil Unit Replacements

Job No: 2971-4
Project No:

Construction Mgr./Contractor: TBA
Consultant::
Project Description: Replacement of the old fan coil units with new ones.The project is estimated to begin on 6/14/2010 and end on 8/13/2010. For more information please contact Project Manager Joe Medeiros at extension 27789.